Level 1
Factory Acceptance Testing (FAT)
Equipment is tested at the manufacturer's facility before it ever ships to site.
- Witnessed tests on switchgear, UPS systems, generators, chillers and CRAH/CRAC units against the approved submittals and the basis of design.
- Catches defects, wiring errors and control-logic issues while they are still cheap and fast to fix — no site logistics, no schedule pressure.
- Produces the FAT report and punch list that become the baseline for everything that follows on site.
Gate to pass: equipment performs to specification and the punch list is closed or formally carried forward.